Geismar Branch IT Buildout — 1. Order & Confirm

Geismar (BlastOne International USA) — 6124 Copperhead Road, Geismar, LA · IT PM Steven Reed · Occupancy / go-live Sep 1, 2026

Milestones & Gates

1 of 17 gates complete. Gates flagged "blocks onsite / occupancy" must clear before crews and staff can work on site. Status date 2026-08-05.

17 gates
  1. Aug 4, 2026
    1d past
    1.2

    Confirm IT budget and Finance / PO authority

    Complete

    Governance, Finance & Procurement · Owner Steven Reed / Josh Kliner · Readiness: Evidence accepted

    Exit / evidence

    Milestones & Gates!row 6 — 7/27 IT Open Items review; Hardware Timeline gate Aug 4.

    Gate status
    Readiness note
  2. Aug 7, 2026
    T-2d
    4.3

    Meraki claimability and license mapping confirmed

    Due <=7 Days

    Core Network · Owner Alexander Home / Ross Keigley · Readiness: Evidence outstanding

    Exit / evidence

    Milestones & Gates!row 10 — Critical Gate Aug 7; licensing notes §7.2.

    Gate status
    Readiness note
  3. Aug 8, 2026
    T-3d
    5.4

    Floor-rack / UPS / Synology physical fit confirmed

    Due <=7 Days

    Rack, Power & IT Closet · Owner Alexander Home / Bob Mouk · Readiness: Evidence outstanding

    Exit / evidence

    Milestones & Gates!row 13 — Critical Gate Aug 8; floor-mount decision §8.

    Gate status
    Readiness note
  4. Aug 8, 2026
    T-3d
    6.2

    Cabling vendor scheduled for Aug 17 start

    Blocks onsite / occupancyDue <=7 Days

    Cabling & Electrical · Owner Joe Levy / Steven Reed · Readiness: Evidence outstanding

    Exit / evidence

    Milestones & Gates!row 15 — Critical Gate Aug 8; Open Action 8.

    Gate status
    Readiness note
  5. Aug 12, 2026
    T-7d
    2.5

    Site readiness confirmed

    Blocks onsite / occupancyDue <=7 Days

    Site Readiness & Logistics · Owner Bob Mouk · Readiness: Evidence outstanding

    Exit / evidence

    Milestones & Gates!row 7 — Hardware Timeline and Critical Gate Aug 12.

    Gate status
    Readiness note
  6. Aug 15, 2026
    T-10d
    4.5

    Network configured in Columbus

    On Track

    Core Network · Owner Joe Levy / Ross Keigley · Readiness: Evidence outstanding

    Exit / evidence

    Milestones & Gates!row 11 — Critical Gate Aug 15.

    Gate status
    Readiness note
  7. Aug 17, 2026
    T-12d
    3.7

    Hand-carry Z3C from Columbus to Geismar

    On Track

    ISP & Temporary Connectivity · Owner Next traveler (Joe / Bob) · Readiness: Evidence outstanding

    Exit / evidence

    Milestones & Gates!row 9 — 8/4 ISP decision; Critical Gate Aug 17.

    Gate status
    Readiness note
  8. Aug 18, 2026
    T-13d
    4.7

    Internal shipment released

    Blocks onsite / occupancyOn Track

    Core Network · Owner Joe Levy / Ross Keigley · Readiness: Evidence outstanding

    Exit / evidence

    Milestones & Gates!row 12 — Critical Gate Aug 18.

    Gate status
    Readiness note
  9. Aug 21, 2026
    T-16d
    5.7

    Rack, power, and UPS readiness accepted

    Blocks onsite / occupancyOn Track

    Rack, Power & IT Closet · Owner Joe Levy / Alexander Home · Readiness: Evidence outstanding

    Exit / evidence

    Milestones & Gates!row 14 — Derived from Aug 21 cabling / rack completion gate.

    Gate status
    Readiness note
  10. Aug 21, 2026
    T-16d
    6.5

    Cabling complete and accepted

    Blocks onsite / occupancyOn Track

    Cabling & Electrical · Owner Joe Levy · Readiness: Evidence outstanding

    Exit / evidence

    Milestones & Gates!row 16 — Critical Gate Aug 21.

    Gate status
    Readiness note
  11. Aug 27, 2026
    T-22d
    9.6

    Printing, label, scanner, and RF Smart validation passed

    On Track

    Printers, Scanners & Labels · Owner Joe Levy / Business Validator · Readiness: Evidence outstanding

    Exit / evidence

    Milestones & Gates!row 18 — Onsite printer / label testing window.

    Gate status
    Readiness note
  12. Aug 28, 2026
    T-23d
    7.7

    Cameras ready: recording, motion sensitivity, retention, and audio controls validated

    On Track

    Cameras & Access Control · Owner Joe Levy / Alexander Home · Readiness: Evidence outstanding

    Exit / evidence

    Milestones & Gates!row 17 — Critical Gate Aug 28.

    Gate status
    Readiness note
  13. Aug 28, 2026
    T-23d
    10.6

    Displays and collaboration room ready

    On Track

    Displays & Collaboration · Owner Joe Levy / Business Validator · Readiness: Evidence outstanding

    Exit / evidence

    Milestones & Gates!row 19 — Go-live validation package.

    Gate status
    Readiness note
  14. Aug 28, 2026
    T-23d
    11.3

    Integrated go-live validation passed

    Blocks onsite / occupancyOn Track

    Deployment, Validation & Go-Live · Owner Steven Reed / Joe Levy · Readiness: Evidence outstanding

    Exit / evidence

    Milestones & Gates!row 20 — Critical Gate Aug 28.

    Gate status
    Readiness note
  15. Aug 31, 2026
    T-26d
    11.6

    Readiness signoff

    Blocks onsite / occupancyOn Track

    Deployment, Validation & Go-Live · Owner Business / IT Approvers · Readiness: Evidence outstanding

    Exit / evidence

    Milestones & Gates!row 21 — Critical Gate Aug 31.

    Gate status
    Readiness note
  16. Sep 1, 2026
    T-27d
    11.7

    Geismar site live

    Blocks onsite / occupancyOn Track

    Deployment, Validation & Go-Live · Owner Steven Reed / Project Team · Readiness: Evidence outstanding

    Exit / evidence

    Milestones & Gates!row 22 — Critical Gate Sep 1.

    Gate status
    Readiness note
  17. No date in source
    TBC
    3.4

    Fiber installed and RJ45 handoff verified

    Date TBD

    ISP & Temporary Connectivity · Owner Rev Fiber / Steven Reed · Readiness: Evidence outstanding

    Exit / evidence

    Milestones & Gates!row 8 — ISP outstanding questions and Rev installation timeline.

    Gate status
    Readiness note