Review & Planner Handoff
Steve's disposition queue. Approve a task for Planner, hold it, or return it for update — then export the approved set as a Planner-ready CSV. Status date 2026-08-05.
Planner handoff preview — exact export rows
0 rowsRead-only. Only tasks with review status Approved for Planner and Planner status Ready for Planner export. Migrated rows are excluded and “Assigned To” is always blank — the recommended assignee travels as a label only.
- 1.3
Reconcile the $55,880 approved model to the $50,175 planning BoM and finalize the order set
OverdueCritical pathPhase 1: Order & Confirm · Governance, Finance & Procurement · source owner Steven Reed · due Aug 4, 2026
Document category-level reconciliation and confirm which remaining lines will be ordered.
Reviewer note / blockerIntegrated Plan!row 10
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Steven Reed — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 1.4
Correct CDW billing owner, bill-to / ship-to, payment terms, and correspondence
In ProgressCritical pathPhase 1: Order & Confirm · Governance, Finance & Procurement · source owner Steven Reed / Alexander Home · due Aug 5, 2026
Change billing owner to Josh, remove Brad, set ship-to, restore terms, and CC CeCe.
Reviewer note / blockerIntegrated Plan!row 11
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Steven Reed — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 1.5
Obtain Lenovo ThinkCentre Neo 50q Gen 6 pricing, availability, and lead time
Not StartedPhase 1: Order & Confirm · Governance, Finance & Procurement · source owner Jimmy Shunk · due TBC
Return quote and lead-time confirmation for model 13HR002GUS.
Reviewer note / blockerIntegrated Plan!row 12
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Jimmy Shunk — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 1.6
Place and confirm remaining critical CDW / hardware orders
Not StartedCritical pathPhase 1: Order & Confirm · Governance, Finance & Procurement · source owner Steven Reed / Ross Keigley · due Aug 8, 2026
Release orders after account corrections and budget reconciliation.
Reviewer note / blockerIntegrated Plan!row 13
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Steven Reed — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 1.7
Run weekly project touchpoint, update plan, RAID, decisions, and evidence
In ProgressGovernance · Governance, Finance & Procurement · source owner Steven Reed · due Sep 1, 2026
Review critical gates and update this workbook each Tuesday.
Reviewer note / blockerIntegrated Plan!row 14
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Steven Reed — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 2.1
Confirm DATA 111 / Room 5 specifics and rack units required by Rev
Not StartedCritical pathPhase 1: Order & Confirm · Site Readiness & Logistics · source owner Bob Mouk · due Aug 8, 2026
Confirm NTD location, fiber entry, top-RU allocation, and room access.
Reviewer note / blockerIntegrated Plan!row 15
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Bob Mouk — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 2.2
Confirm building access, occupancy readiness, alarm status, and work windows
Not StartedCritical pathPhase 2: Receive & Configure · Site Readiness & Logistics · source owner Bob Mouk · due Aug 12, 2026
Confirm access dates and installer work windows.
Reviewer note / blockerIntegrated Plan!row 16
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Bob Mouk — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 2.3
Confirm cubes, offices, furniture, desk layout, and monitor quantities
Not StartedCritical pathPhase 2: Receive & Configure · Site Readiness & Logistics · source owner Bob Mouk / Jim Gooden · due Aug 12, 2026
Confirm five-office / warehouse layout and shipment timing.
Reviewer note / blockerIntegrated Plan!row 17
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Bob Mouk — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 2.4
Coordinate receiving coverage and delivery constraints for the gated site
In ProgressPhase 2: Receive & Configure · Site Readiness & Logistics · source owner Spike Graham · due Aug 21, 2026
Provide carrier instructions and named receiving contact for each shipment.
Reviewer note / blockerIntegrated Plan!row 18
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Spike Graham — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 2.5
Site readiness confirmed
Not StartedCritical pathPhase 2: Receive & Configure · Site Readiness & Logistics · source owner Bob Mouk · due Aug 12, 2026
Document readiness decision and remaining exceptions.
Reviewer note / blockerIntegrated Plan!row 19
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Bob Mouk — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 3.2
Reply to Rev technical questions: handoff method, NTD, RJ45, contention, and RU
Not StartedPhase 1: Order & Confirm · ISP & Temporary Connectivity · source owner Steven Reed · due Aug 7, 2026
Send consolidated questions and obtain written answers.
Reviewer note / blockerIntegrated Plan!row 21
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Steven Reed — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 3.3
Complete Rev splicing, cable pull, wall penetration, and install scheduling
In ProgressPhase 2: Receive & Configure · ISP & Temporary Connectivity · source owner Neal Dronet / Brent · due Sep 1, 2026
Obtain dated splice and install appointments; coordinate building access.
Reviewer note / blockerIntegrated Plan!row 22
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Neal Dronet — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 3.4
Fiber installed and RJ45 handoff verified
Not StartedPhase 3: Ship & Install · ISP & Temporary Connectivity · source owner Rev Fiber / Steven Reed · due TBC
Set target after Rev confirms splice and install dates.
Reviewer note / blockerIntegrated Plan!row 23
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Rev Fiber — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 3.5
Confirm spare Meraki Z3C, active SIM, configuration, and handoff readiness
Not StartedCritical pathPhase 2: Receive & Configure · ISP & Temporary Connectivity · source owner Ross Keigley · due Aug 14, 2026
Locate unit, verify SIM/service, test Wi-Fi/ports, and package for travel.
Reviewer note / blockerIntegrated Plan!row 24
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Ross Keigley — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 3.6
Provide Z3C serial number and add device to the Geismar site
Not StartedCritical pathPhase 2: Receive & Configure · ISP & Temporary Connectivity · source owner Alexander Home / Ross Keigley · due Aug 14, 2026
Record serial and assign the device to the site.
Reviewer note / blockerIntegrated Plan!row 25
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Alexander Home — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 3.7
Hand-carry Z3C from Columbus to Geismar
Not StartedCritical pathPhase 3: Ship & Install · ISP & Temporary Connectivity · source owner Next traveler (Joe / Bob) · due Aug 17, 2026
Confirm named traveler and possession before departure.
Reviewer note / blockerIntegrated Plan!row 26
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Next traveler (Joe — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 3.8
Install Z3C and perform onsite 4G / Day-1 connectivity qualification
Not StartedCritical pathPhase 3: Ship & Install · ISP & Temporary Connectivity · source owner Joe Levy / Bob Mouk · due Aug 18, 2026
Plug in, validate Wi-Fi / Ethernet, printer access, and signal strength.
Reviewer note / blockerIntegrated Plan!row 27
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 3.9
Decide whether an external 4G antenna is required and install if approved
Not StartedPhase 3: Ship & Install · ISP & Temporary Connectivity · source owner Alexander Home · due Aug 21, 2026
Use signal qualification to make the antenna decision.
Reviewer note / blockerIntegrated Plan!row 28
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Alexander Home — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 3.11
Return Z3C after stable production connectivity is established
On HoldPhase 4: Validate & Go-Live · ISP & Temporary Connectivity · source owner Ross Keigley / Alexander Home · due TBC
Set return trigger after fiber or stable permanent service is accepted.
Reviewer note / blockerIntegrated Plan!row 30
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Ross Keigley — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 4.2
Receive and inspect core network hardware in Columbus
In ProgressCritical pathPhase 2: Receive & Configure · Core Network · source owner Ross Keigley / Joe Levy · due Aug 13, 2026
Log receipts, serials, condition, and missing items.
Reviewer note / blockerIntegrated Plan!row 32
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Ross Keigley — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 4.3
Meraki claimability and license mapping confirmed
Not StartedCritical pathPhase 2: Receive & Configure · Core Network · source owner Alexander Home / Ross Keigley · due Aug 7, 2026
Confirm claimability and map MS225, MS120, and MX67C licenses.
Reviewer note / blockerIntegrated Plan!row 33
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Alexander Home — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 4.4
Claim, license, configure on destination subnet, label, and bench test
In ProgressCritical pathPhase 2: Receive & Configure · Core Network · source owner Joe Levy / Ross Keigley · due Aug 15, 2026
Complete claim/configuration checklist and document bench-test results.
Reviewer note / blockerIntegrated Plan!row 34
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 4.5
Network configured in Columbus
Not StartedCritical pathPhase 2: Receive & Configure · Core Network · source owner Joe Levy / Ross Keigley · due Aug 15, 2026
Approve release to internal shipment.
Reviewer note / blockerIntegrated Plan!row 35
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 4.6
Palletize and prepare configured gear for protected shipment
Not StartedPhase 3: Ship & Install · Core Network · source owner Joe Levy / Ross Keigley · due Aug 19, 2026
Pack, inventory, label, and protect configured equipment.
Reviewer note / blockerIntegrated Plan!row 36
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 4.7
Internal shipment released
Not StartedCritical pathPhase 3: Ship & Install · Core Network · source owner Joe Levy / Ross Keigley · due Aug 18, 2026
Confirm release, carrier, tracking, and receiving contact.
Reviewer note / blockerIntegrated Plan!row 37
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 4.8
Ship configured gear from Columbus to Geismar
Not StartedCritical pathPhase 3: Ship & Install · Core Network · source owner Ross Keigley · due Aug 21, 2026
Track shipment through verified onsite receipt.
Reviewer note / blockerIntegrated Plan!row 38
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Ross Keigley — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 4.9
Install, rack, patch, and turn up the production network onsite
Not StartedCritical pathPhase 3: Ship & Install · Core Network · source owner Joe Levy · due Aug 26, 2026
Install MX67C, switches, APs, and confirm management visibility.
Reviewer note / blockerIntegrated Plan!row 39
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 4.10
Validate LAN, Wi-Fi coverage, Internet, and 4G redundancy
Not StartedCritical pathPhase 4: Validate & Go-Live · Core Network · source owner Joe Levy / Alexander Home · due Aug 28, 2026
Run production connectivity and failover tests.
Reviewer note / blockerIntegrated Plan!row 40
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 5.2
Place rack / UPS / licensing / patch-cable order
Not StartedCritical pathPhase 1: Order & Confirm · Rack, Power & IT Closet · source owner Steven Reed / Ross Keigley · due Aug 8, 2026
Issue PO and confirm lead times and ship-to Geismar.
Reviewer note / blockerIntegrated Plan!row 42
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Steven Reed — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 5.3
Receive and inspect physical rack / UPS items
Not StartedCritical pathPhase 2: Receive & Configure · Rack, Power & IT Closet · source owner Spike Graham / Bob Mouk · due Aug 13, 2026
Confirm quantities, damage status, and secure storage.
Reviewer note / blockerIntegrated Plan!row 43
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Spike Graham — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 5.4
Floor-rack / UPS / Synology physical fit confirmed
Not StartedCritical pathPhase 2: Receive & Configure · Rack, Power & IT Closet · source owner Alexander Home / Bob Mouk · due Aug 8, 2026
Validate room dimensions, RU allocation, power, and floor placement.
Reviewer note / blockerIntegrated Plan!row 44
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Alexander Home — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 5.5
Schedule electrician for dedicated 20A rack circuit
Not StartedCritical pathPhase 1: Order & Confirm · Rack, Power & IT Closet · source owner Joe Levy / Alexander Home · due Aug 8, 2026
Book electrician to start when Joe is onsite Aug 17.
Reviewer note / blockerIntegrated Plan!row 45
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 5.6
Install rack, UPS, shelves, patching, cable management, and 20A power
Not StartedCritical pathPhase 3: Ship & Install · Rack, Power & IT Closet · source owner Joe Levy / Electrician · due Aug 21, 2026
Complete physical installation and power readiness checks.
Reviewer note / blockerIntegrated Plan!row 46
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 5.7
Rack, power, and UPS readiness accepted
Not StartedCritical pathPhase 3: Ship & Install · Rack, Power & IT Closet · source owner Joe Levy / Alexander Home · due Aug 21, 2026
Release rack for production network installation.
Reviewer note / blockerIntegrated Plan!row 47
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 6.1
Finalize cabling / electrical vendor quote, scope, insurance, access, and field plan
Not StartedCritical pathPhase 1: Order & Confirm · Cabling & Electrical · source owner Joe Levy / Steven Reed · due Aug 8, 2026
Select vendor or activate BlastOne backup-cabler path.
Reviewer note / blockerIntegrated Plan!row 48
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 6.2
Cabling vendor scheduled for Aug 17 start
Not StartedCritical pathPhase 1: Order & Confirm · Cabling & Electrical · source owner Joe Levy / Steven Reed · due Aug 8, 2026
Confirm named crew, lift requirements, start time, and duration.
Reviewer note / blockerIntegrated Plan!row 49
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 6.3
Confirm 48-run Cat6 plenum drop map, service loops, patch-cord lengths, and labels
Not StartedCritical pathPhase 2: Receive & Configure · Cabling & Electrical · source owner Joe Levy / Alexander Home · due Aug 12, 2026
Issue marked floor plan and resolve patch-cord unit discrepancy.
Reviewer note / blockerIntegrated Plan!row 50
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 6.4
Install 48 Cat6 plenum runs; test and label drops; complete display-power preparation
Not StartedCritical pathPhase 3: Ship & Install · Cabling & Electrical · source owner Cabling vendor / Joe Levy · due Aug 21, 2026
Execute field work and capture per-drop test results.
Reviewer note / blockerIntegrated Plan!row 51
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Cabling vendor — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 6.5
Cabling complete and accepted
Not StartedCritical pathPhase 3: Ship & Install · Cabling & Electrical · source owner Joe Levy · due Aug 21, 2026
Approve test results and release dependent installs.
Reviewer note / blockerIntegrated Plan!row 52
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 7.1
Verify Louisiana privacy, audio-recording, and signage requirements
Not StartedCritical pathPhase 1: Order & Confirm · Cameras & Access Control · source owner Joe Levy · due Aug 8, 2026
Document permitted configuration and signage / audio controls.
Reviewer note / blockerIntegrated Plan!row 53
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 7.2
Finalize and order 8 x 5MP Axis cameras, Synology NVR, and surveillance drives
Not StartedPhase 1: Order & Confirm · Cameras & Access Control · source owner Joe Levy / Alexander Home · due Aug 8, 2026
Confirm exact models, quantities, pricing, and delivery dates.
Reviewer note / blockerIntegrated Plan!row 54
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 7.3
Receive and inspect camera / NVR hardware
Not StartedPhase 2: Receive & Configure · Cameras & Access Control · source owner Joe Levy / Spike Graham · due Aug 7, 2026
Confirm receipt and serial inventory; rebaseline if order lead time changes.
Reviewer note / blockerIntegrated Plan!row 55
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 7.4
Select and configure recorder, surveillance drives, retention, and motion settings
Not StartedPhase 2: Receive & Configure · Cameras & Access Control · source owner Joe Levy / Alexander Home · due Aug 15, 2026
Configure NVR, motion sensitivity, retention, and audio-disabled policy.
Reviewer note / blockerIntegrated Plan!row 56
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 7.5
Confirm camera placement, mounting height, and final fields of view after racking
Not StartedPhase 3: Ship & Install · Cameras & Access Control · source owner Joe Levy / Bob Mouk · due Aug 24, 2026
Mark ingress / egress, gear-parking, and interior positions.
Reviewer note / blockerIntegrated Plan!row 57
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 7.6
Install, aim, and connect cameras after cabling is ready
Not StartedPhase 3: Ship & Install · Cameras & Access Control · source owner Joe Levy / Installer · due Aug 27, 2026
Mount cameras, validate focus / field of view, and connect to NVR.
Reviewer note / blockerIntegrated Plan!row 58
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 7.7
Cameras ready: recording, motion sensitivity, retention, and audio controls validated
Not StartedPhase 4: Validate & Go-Live · Cameras & Access Control · source owner Joe Levy / Alexander Home · due Aug 28, 2026
Attach validation evidence to readiness package.
Reviewer note / blockerIntegrated Plan!row 59
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 7.8
Confirm cardkey vs. key entry and engage locksmith for access control
On HoldPhase 2 / Deferred · Cameras & Access Control · source owner Bob Mouk · due TBC
Confirm business decision, door count, controller consolidation, and locksmith.
Reviewer note / blockerIntegrated Plan!row 60
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Bob Mouk — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 7.9
Plan and execute Phase 2 access-control implementation
On HoldPhase 2 / Deferred · Cameras & Access Control · source owner TBD · due TBC
Assign delivery owner and schedule after the access method is approved.
Reviewer note / blockerIntegrated Plan!row 61
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee TBD — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 8.1
Confirm Geismar user roster, start dates, and device quantities
Not StartedPhase 1: Order & Confirm · New Hire & End-User · source owner Ross Keigley · due Aug 10, 2026
Identify Geismar users versus Norfolk / Columbus hires and final device count.
Reviewer note / blockerIntegrated Plan!row 62
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Ross Keigley — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 8.2
New hires attend Columbus training
Not StartedPhase 2: Receive & Configure · New Hire & End-User · source owner Business / Hiring Team · due Aug 12, 2026
Confirm attendees and arrival schedule.
Reviewer note / blockerIntegrated Plan!row 63
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Business — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 8.3
Image, issue, and complete user setup for new-hire laptops in Columbus
Not StartedPhase 2: Receive & Configure · New Hire & End-User · source owner Ross Keigley · due Aug 12, 2026
Prepare laptops before trainees leave Columbus.
Reviewer note / blockerIntegrated Plan!row 64
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Ross Keigley — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 8.4
Confirm desk / monitor quantities and time direct shipment to site build-out
Not StartedPhase 2: Receive & Configure · New Hire & End-User · source owner Joe Levy / Steven Reed · due Aug 12, 2026
Resolve quantity discrepancy and release monitors / peripherals at the correct time.
Reviewer note / blockerIntegrated Plan!row 65
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 8.5
Receive office workstation bundles, monitors, docks, and peripherals
Not StartedPhase 2: Receive & Configure · New Hire & End-User · source owner Spike Graham / Ross Keigley · due Aug 18, 2026
Track direct shipments and record shortages / damage.
Reviewer note / blockerIntegrated Plan!row 66
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Spike Graham — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 8.6
Stage and install office workstations and standardized peripherals
Not StartedPhase 3: Ship & Install · New Hire & End-User · source owner Joe Levy / Ross Keigley · due Aug 27, 2026
Install dual monitors, docks, Logitech Bolt devices, webcam, WH62 headset, cables, and surge protection.
Reviewer note / blockerIntegrated Plan!row 67
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 8.7
Order, receive, and configure the warehouse Lenovo desktop in Columbus
Not StartedPhase 2: Receive & Configure · New Hire & End-User · source owner Ross Keigley · due TBC
Set dates after Lenovo quote and lead time are received.
Reviewer note / blockerIntegrated Plan!row 68
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Ross Keigley — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 8.8
Install warehouse workstation and MS120-8FP PoE switch
Not StartedPhase 3: Ship & Install · New Hire & End-User · source owner Joe Levy · due Aug 27, 2026
Install PC, local switch, label printers, and connected warehouse devices.
Reviewer note / blockerIntegrated Plan!row 69
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 9.1
Confirm redeployable printer inventory and service / toner transfer
Not StartedPhase 1: Order & Confirm · Printers, Scanners & Labels · source owner Ross Keigley · due Aug 8, 2026
Confirm the two redeployed units and transfer service / toner coverage.
Reviewer note / blockerIntegrated Plan!row 70
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Ross Keigley — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 9.2
Confirm 4x6 / 2x4 label requirements, DuraScan D860 details, and RF Smart devices
Not StartedPhase 1: Order & Confirm · Printers, Scanners & Labels · source owner Steven Reed · due Aug 8, 2026
Confirm labels with Trevor and send scanner information to Shaun.
Reviewer note / blockerIntegrated Plan!row 71
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Steven Reed — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 9.3
Order / transfer office Canon, warehouse laser, and two Zebra label printers
Not StartedPhase 1: Order & Confirm · Printers, Scanners & Labels · source owner Ross Keigley · due Aug 8, 2026
Release new Canon order and redeployment logistics.
Reviewer note / blockerIntegrated Plan!row 72
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Ross Keigley — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 9.4
Receive printers, labels, supplies, scanners, and related devices
Not StartedPhase 2: Receive & Configure · Printers, Scanners & Labels · source owner Spike Graham / Ross Keigley · due Aug 12, 2026
Inventory devices and supplies at receipt.
Reviewer note / blockerIntegrated Plan!row 73
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Spike Graham — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 9.5
Stage, install, and configure office / warehouse printing and scanning devices
Not StartedPhase 3: Ship & Install · Printers, Scanners & Labels · source owner Joe Levy / Ross Keigley · due Aug 27, 2026
Prepare devices, install onsite, load labels, and connect to the correct network.
Reviewer note / blockerIntegrated Plan!row 74
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 9.6
Printing, label, scanner, and RF Smart validation passed
Not StartedPhase 4: Validate & Go-Live · Printers, Scanners & Labels · source owner Joe Levy / Business Validator · due Aug 27, 2026
Capture sample outputs and business validation.
Reviewer note / blockerIntegrated Plan!row 75
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 10.1
Confirm display quantities, sizes, mounts, reused TV + cart, and shipping path
Not StartedPhase 1: Order & Confirm · Displays & Collaboration · source owner Steven Reed / Ross Keigley · due Aug 8, 2026
Confirm 65-inch / 55-inch requirements and reduce order for the reused unit.
Reviewer note / blockerIntegrated Plan!row 76
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Steven Reed — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 10.2
Receive TVs, mounts, and dashboard display controllers
In ProgressPhase 2: Receive & Configure · Displays & Collaboration · source owner Spike Graham / Ross Keigley · due Aug 13, 2026
Track TVs / mounts; coordinate gated-site receiving.
Reviewer note / blockerIntegrated Plan!row 77
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Spike Graham — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 10.4
Mount TVs and install dashboard / display controllers
Not StartedPhase 3: Ship & Install · Displays & Collaboration · source owner Installer / Joe Levy · due Aug 26, 2026
Mount displays, connect power/data, and install micro-PC controllers.
Reviewer note / blockerIntegrated Plan!row 79
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Installer — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 10.5
Configure and test Room Kit Mini, dashboards, HDMI, and consumer-TV network restrictions
Not StartedPhase 3: Ship & Install · Displays & Collaboration · source owner Joe Levy / Alexander Home · due Aug 28, 2026
Validate calls, content sharing, dashboards, and restricted TV network access.
Reviewer note / blockerIntegrated Plan!row 80
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 10.6
Displays and collaboration room ready
Not StartedPhase 4: Validate & Go-Live · Displays & Collaboration · source owner Joe Levy / Business Validator · due Aug 28, 2026
Include validation evidence in readiness package.
Reviewer note / blockerIntegrated Plan!row 81
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 11.1
Joe onsite for install support
Not StartedPhase 3: Ship & Install · Deployment, Validation & Go-Live · source owner Joe Levy · due Aug 21, 2026
Confirm travel, access, vendor start times, and first-day rack organization.
Reviewer note / blockerIntegrated Plan!row 82
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 11.2
Complete full onsite installation window
Not StartedCritical pathPhase 3: Ship & Install · Deployment, Validation & Go-Live · source owner Joe Levy / Project Team · due Aug 28, 2026
Coordinate integrated installation across network, cameras, end-user, printers, and displays.
Reviewer note / blockerIntegrated Plan!row 83
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Joe Levy — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 11.3
Integrated go-live validation passed
Not StartedCritical pathPhase 4: Validate & Go-Live · Deployment, Validation & Go-Live · source owner Steven Reed / Joe Levy · due Aug 28, 2026
Execute integrated validation and document exceptions.
Reviewer note / blockerIntegrated Plan!row 84
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Steven Reed — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 11.4
Resolve validation exceptions within the remediation buffer
Not StartedCritical pathPhase 4: Validate & Go-Live · Deployment, Validation & Go-Live · source owner Steven Reed / Joe Levy · due Aug 31, 2026
Prioritize go-live blockers and document accepted residual items.
Reviewer note / blockerIntegrated Plan!row 85
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Steven Reed — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 11.5
Conduct readiness review and prepare approval package
Not StartedCritical pathPhase 4: Validate & Go-Live · Deployment, Validation & Go-Live · source owner Steven Reed · due Aug 31, 2026
Compile evidence, RAID disposition, support ownership, and outstanding exceptions.
Reviewer note / blockerIntegrated Plan!row 86
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Steven Reed — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 11.6
Readiness signoff
Not StartedCritical pathPhase 4: Validate & Go-Live · Deployment, Validation & Go-Live · source owner Business / IT Approvers · due Aug 31, 2026
Record approval or documented conditional approval.
Reviewer note / blockerIntegrated Plan!row 87
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Business — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 11.7
Geismar site live
Not StartedCritical pathPhase 4: Validate & Go-Live · Deployment, Validation & Go-Live · source owner Steven Reed / Project Team · due Sep 1, 2026
Confirm production service and communicate go-live status.
Reviewer note / blockerIntegrated Plan!row 88
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee Steven Reed — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.
- 11.8
Define post-go-live support, hypercare, handoff, and project-closeout ownership
Not StartedPhase 4: Validate & Go-Live · Deployment, Validation & Go-Live · source owner TBD · due TBC
Assign support owner, support window, escalation path, acceptance evidence, and closeout date.
Reviewer note / blockerIntegrated Plan!row 89
Review dispositionPlanner handoffGate closed — Planner handoff unlocks only on “Approved for Planner”.
Recommended assignee TBD — a tag only. The Planner export leaves “Assigned To” blank so Steve assigns in Planner.