Geismar Branch IT Buildout — 1. Order & Confirm

Geismar (BlastOne International USA) — 6124 Copperhead Road, Geismar, LA · IT PM Steven Reed · Occupancy / go-live Sep 1, 2026

RAID Register

Risks, assumptions, issues, decisions, dependencies and gaps — kept in separate registers so nothing hides inside a generic list.

19 items
Risk

Risks

8

Could happen and would hurt delivery. Mitigate before it becomes an issue.

  • R-01Critical

    Rev is at splicing and the realistic estimate is about one month, driven by splice scheduling, cable pull, and wall penetration.

    Mitigation / next step

    Related WBS 3.2-3.9 · RAID Log!row 6 — 8/4 Rev quote and ISP discussion.

    Status
    Rating
    Owner
    Due / review
    Aug 7, 2026
    Impact / likelihood
    High / High
  • R-02Critical

    Aug 17 field start and Aug 21 completion are critical predecessors for network, cameras, and displays.

    Mitigation / next step

    Related WBS 6.1-6.5 · RAID Log!row 7 — Open Action 8; Critical Gate Aug 8.

    Status
    Rating
    Owner
    Due / review
    Aug 8, 2026
    Impact / likelihood
    High / High
  • R-03Critical

    Quote is technically approved, but billing owner, ship-to, payment terms, and account contacts require correction.

    Mitigation / next step

    Related WBS 1.4, 5.2-5.4 · RAID Log!row 8 — 8/4 ISP discussion; CDW Quote #6B0VJWH.

    Status
    Rating
    Owner
    Due / review
    Aug 8, 2026
    Impact / likelihood
    High / High
  • R-04High

    Access, occupancy, alarm status, cubes/offices, furniture, and wall / mount readiness are not yet confirmed.

    Mitigation / next step

    Related WBS 2.1-2.5 · RAID Log!row 9 — Stakeholder register; Critical Gate Aug 12.

    Status
    Rating
    Owner
    Due / review
    Aug 12, 2026
    Impact / likelihood
    High / Medium
  • R-05High

    Spare unit, active SIM, serial, site assignment, and named traveler remain open.

    Mitigation / next step

    Related WBS 3.5-3.8 · RAID Log!row 10 — 8/4 ISP discussion; Open Actions 1-2 and 7.

    Status
    Rating
    Owner
    Due / review
    Aug 14, 2026
    Impact / likelihood
    High / Medium
  • R-06High

    5MP specification is corrected, but hardware order and Louisiana privacy / audio / signage review remain open.

    Mitigation / next step

    Related WBS 7.1-7.7 · RAID Log!row 11 — 7/30 IT Sync Up; Open Action 12.

    Status
    Rating
    Owner
    Due / review
    Aug 8, 2026
    Impact / likelihood
    Medium / High
  • R-07High

    The review references five workstations with three initial, while the detailed scope states five office plus one warehouse.

    Mitigation / next step

    Related WBS 2.3, 8.1, 8.4 · RAID Log!row 12 — 7/30 traceability and §11.1.

    Status
    Rating
    Owner
    Due / review
    Aug 12, 2026
    Impact / likelihood
    Medium / High
  • R-08Medium

    Local delivery zones do not consistently recognize 6124 Copperhead Road; onsite receiving must be coordinated.

    Mitigation / next step

    Related WBS 2.4 · RAID Log!row 13 — Staffing §3.1 and shipping notes §11.3.

    Status
    Rating
    Owner
    Due / review
    Aug 5, 2026
    Impact / likelihood
    Medium / Medium
Issue

Issues

2

Already happening. Needs an owner and a next step now.

  • I-01Critical

    Approved IT ceiling is $55,880; planning BoM is $50,175 and excludes ISP. Final order set remains open.

    Mitigation / next step

    Related WBS 1.3 · RAID Log!row 14 — 7/31 BoM email; Open Action 11.

    Status
    Rating
    Owner
    Due / review
    Aug 4, 2026 · past due
    Impact / likelihood
    High / High
  • I-02Critical

    Bradley Gooden remains on the quote; billing owner should be Josh Kliner; Net 30 is expired.

    Mitigation / next step

    Related WBS 1.4 · RAID Log!row 15 — 8/4 ISP discussion; Quote #6B0VJWH.

    Status
    Rating
    Owner
    Due / review
    Aug 5, 2026
    Impact / likelihood
    High / High
Decision

Decisions

2

Choices made or pending. Closed decisions stay visible for traceability.

  • DC-01Critical

    The Aug 4 decision supersedes Starlink mounting, landlord roof-permission work, and the mobile-rack plan.

    Mitigation / next step

    Related WBS 3.5-3.10 · RAID Log!row 23 — 8/4 ISP discussion.

    Status
    Rating
    Owner
    Due / review
    Aug 4, 2026
    Impact / likelihood
    High / High
  • DC-02High

    CGNAT is acceptable; static IP is not required. Remaining Rev handoff details still need confirmation.

    Mitigation / next step

    Related WBS 3.2-3.4 · RAID Log!row 24 — 8/4 ISP discussion.

    Status
    Rating
    Owner
    Due / review
    Aug 4, 2026
    Impact / likelihood
    Medium / High
Assumption

Assumptions

1

Believed true but unverified. Verify or convert to a risk.

  • A-01High

    The date depends on site readiness, vendor scheduling, hardware arrival, and internal shipment gates holding.

    Mitigation / next step

    Related WBS 11.7 · RAID Log!row 20 — Hardware Timeline and Review document §12.

    Status
    Rating
    Owner
    Due / review
    Aug 12, 2026
    Impact / likelihood
    High / Medium
Dependency

Dependencys

2

External commitments the plan relies on.

  • D-01Critical

    Network turn-up and camera installation depend on completed cabling, power, rack installation, and accepted test results.

    Mitigation / next step

    Related WBS 4.9, 5.7, 6.5, 7.6 · RAID Log!row 21 — Hardware Timeline critical path.

    Status
    Rating
    Owner
    Due / review
    Aug 21, 2026
    Impact / likelihood
    High / High
  • D-02Critical

    Meraki devices must be claimed, licensed, configured, labeled, and bench tested before shipment to Geismar.

    Mitigation / next step

    Related WBS 4.3-4.8 · RAID Log!row 22 — Configuration approach and Critical Gate Aug 15.

    Status
    Rating
    Owner
    Due / review
    Aug 15, 2026
    Impact / likelihood
    High / High
Gap

Gaps

4

Source conflicts and missing information — nothing invented to fill them.

  • G-01High

    Narrative states 12-inch rack and 6-inch desk cords; CDW quote contains 1-foot rack and 6-foot desk cords.

    Mitigation / next step

    Related WBS 6.3 · RAID Log!row 16 — Cabling §9.1 versus CDW quote §8.1.

    Status
    Rating
    Owner
    Due / review
    Aug 8, 2026
    Impact / likelihood
    Medium / High
  • G-02High

    Approved model shows $1,700 unit x 3 but a $2,200 total; this may represent a redeployment offset or a source error.

    Mitigation / next step

    Related WBS 1.3, 9.1-9.3 · RAID Log!row 17 — Approved IT budget model §4.1.

    Status
    Rating
    Owner
    Due / review
    Aug 8, 2026
    Impact / likelihood
    Medium / High
  • G-03Medium

    Cardkey vs. key entry, locksmith, door count, controller consolidation, dates, and delivery owner remain open.

    Mitigation / next step

    Related WBS 7.8-7.9 · RAID Log!row 18 — 7/15 pre-deploy; Open Action 13.

    Status
    Rating
    Owner
    Due / review
    No date in source
    Impact / likelihood
    Medium / Medium
  • G-04Medium

    Reviewed sources identify go-live but not hypercare duration, support owner, escalation path, handoff, or closure evidence.

    Mitigation / next step

    Related WBS 11.8 · RAID Log!row 19 — Comprehensive plan conversion gap.

    Status
    Rating
    Owner
    Due / review
    No date in source
    Impact / likelihood
    Medium / Medium